Finish schedules for new construction (free template)
The short answer
A finish schedule is a room-by-room table listing every finish in a house, such as flooring, paint, tile, countertops and hardware, with the manufacturer, product, color, size and quantity for each. Builders use it to price, order and install the right material in the right place. A free template is below.
Related serviceInterior design systems for new construction

On a new build, the finish schedule ties design to purchasing. The plans show where things go. The finish schedule says what they are, who supplies them and when they have to be ordered. Without one, those answers live in text messages and somebody's memory.
This guide explains what belongs in a finish schedule and how to fill one out. The template is pre-filled with finishes from our Forest Lawn project. Writing finish schedules and selection packages is also a core part of the new construction interior design Native Plans does for builders.
Native finish schedule template (CSV)
Room-by-room rows with columns for manufacturer, product, finish, size, quantity, supplier, lead time, order-by date and status. Example rows come from the Forest Lawn finish palette. Lead times are blank on purpose: confirm them with your suppliers. Opens in Excel, Numbers and Google Sheets.
Want it filled in for your plan? Send the plan set and we'll return a finish schedule your purchasing team can order from.
What is a schedule of finishes?
A schedule of finishes, or finish schedule, is a table keyed to the plans, the way a door schedule or a window schedule is. Rows are items or rooms. Columns are the facts you need about each one.
There are two versions. A basic room finish schedule, often found on the plan set, lists the floor, base, walls and ceiling of each room in general terms, such as hardwood or painted drywall. An interior design finish schedule goes down to product level: manufacturer, model, color code and size. A buyer placing orders needs the second one. An estimator pricing early may only have the first.
What are the different types of house finishes?
The word covers any surface or visible component that completes the construction. A workable grouping:
- Floors: wood, tile, carpet, stone and the transitions between them.
- Walls and ceilings: paint, wallpaper, plaster or limewash, tile, wood paneling.
- Trim and millwork: base, casing, crown, paneling, built-ins, stair parts.
- Cabinetry and countertops: door style, finish, hardware, stone or quartz, edge profiles.
- Tile: floors, showers and backsplashes, with grout and trim pieces.
- Hardware and plumbing trim: pulls, hinges, door hardware, faucets, shower trim and accessories.
- Fixtures and equipment: plumbing fixtures, lighting and appliances. Some teams keep these on separate schedules.
Pick one structure and keep it. The schedule is easier to use when every finish is in one place and each item appears once.
What goes in a finish schedule?
The template has 14 columns. Each is there because someone in the field or in purchasing would otherwise have to ask.
| Column | What to record | Who needs it |
|---|---|---|
| Area | The room or zone, using the names on the plans. | Everyone |
| Item | What is being finished: flooring, wall paint, vanity top. | Everyone |
| Location | Where in the area, if not all of it: the islands, the shower, one wall. | Installer |
| Plan ref | The sheet or detail where the item is drawn. | Estimator, field |
| Manufacturer, Product/Model | The exact product name and model number, not a description. | Purchasing, supplier |
| Finish/Color | The color or finish name and code, with sheen for paint. | Installer, supplier |
| Size | Dimensions, thickness, plank or tile size, where it matters. | Supplier, installer |
| Qty | From a takeoff, with waste noted separately. | Purchasing |
| Supplier | Who you buy it from. | Purchasing |
| Lead time | The supplier's confirmed lead time, with the date you confirmed it. | Purchasing, superintendent |
| Order-by date | The date the item must be ordered to arrive when it is needed. | Purchasing, superintendent |
| Status | Open, selected, approved, ordered, delivered or installed. | Everyone |
| Notes | Conditions, approvals and open questions. | Everyone |
Lead time and order-by date are the two columns most schedules skip. We left lead times blank because they vary by supplier and change over time. Get the number from the supplier, write down the date they gave it, and work out the order-by date from there: the date the item must be on site, minus the confirmed lead time, minus a buffer you choose.
How do you fill out a finish schedule?
- Start from the plans. List every room by the name on the floor plan, so the schedule and the drawings use the same vocabulary.
- Add one row per finish per room. A kitchen gets many rows and a closet gets a few. Write the item before the product, so gaps show.
- Use specific names. 'White paint' is not a finish. A manufacturer, a color name and a code is.
- Fill in what you know and mark the rest Open. A row with no product and a status of Open tells the builder what is undecided.
- Take quantities from a takeoff, not a guess, and note waste separately.
- Add supplier, confirmed lead time and order-by date for anything that has to be ordered ahead.
- Give the schedule one owner and date every revision. Issue changes as a new version so the field is never working from an old one.
What does a filled-in finish schedule look like?
The template ships with rows from the finish palette of the Forest Lawn house in Brentwood, Tennessee. These are some of them.
| Area | Item | Product and finish | What the Notes column flags |
|---|---|---|---|
| Whole house | Wood flooring | Calais by Fabrica, Normandy Oak | Plank size, thickness and transitions |
| Whole house | Wall paint | Sherwin-Williams SW 7008 Alabaster | Sheen by room |
| Kitchen | Cabinetry | Shaker door style, Limewash finish | Manufacturer, construction, approved finish sample |
| Kitchen | Countertop, islands | Bianco Drift quartz | Slab count and seams, with the fabricator |
| Primary bathroom | Vanities | Calacatta Classique | Whether it describes the cabinet, the top or both |
| Primary bathroom | Hardware and plumbing trim | Satin brass | Which items take the finish |
| Primary bathroom | Shower tile | Zarah | Manufacturer, tile size, grout, trim pieces |
| Primary bedroom | Moldings | Egret White | Paint manufacturer, color code and sheen |
Plenty of cells in the file are blank, on purpose. A schedule in progress has open items, and the Status and Notes columns exist to say what is still open. A blank cell is better than a guess.
What are the most common finish schedule mistakes?
Most schedule failures are ordinary ones, and ordinary mistakes are the ones that reach the job site.
- Describing instead of naming. "White tile" cannot be ordered. A manufacturer, a product name and a color code can.
- Calling one finish three things. If brass is "satin brass" on the plumbing order, "brushed brass" on the hardware order and "aged brass" on the lighting order, the house ends up with three golds. Pick one name and use it everywhere.
- Leaving out what sits behind the finish: substrates, trim pieces, transitions, grout and setting materials. Tile without its trim pieces is an incomplete order.
- Skipping the plan reference, so nobody can trace a row back to a drawing.
- Running two versions with two owners, so the field and the office price and order from different lists.
When should a finish schedule be done?
It starts early and fills in as decisions are made. The first version is a pricing tool: categories and allowances by room. The second adds products and becomes a purchasing tool, and it has to exist before the trades that depend on it. After ordering, the third version is a record of what was installed, which a builder will want for warranty and service calls. Our guide to when to make selections in a new build goes through the timing by construction phase. The short version: the finish schedule is where decide-by dates live, so start it before framing, not after.
Who writes the finish schedule?
On builder-run projects it is often the builder's office or a purchasing lead, working from the builder's standards or the buyer's choices. On others an interior designer writes it. What matters is one owner and one current version.
A designer who specifies finishes needs to know the builder's suppliers, allowances and schedule. A builder who specifies needs to know the design intent. Native writes finish schedules and selection packages alongside the plans, so the schedule and the drawings share room names and agree on openings.
Native's take
A finish schedule is a purchasing document that happens to be about design. Someone in purchasing who never saw the design presentation should be able to place the orders from it.
If a row needs a phone call to interpret, the row is not finished.
If you want this done for your own product, see how our interior design service documents finishes, fixtures and purchasing information for builders. The template above is free to use either way. For how the schedule sits alongside the drawings, read the sheet-by-sheet guide to residential plan sets.
G-595Put it to work
Want this done for your next project?
Native Plans works as the design department for residential builders and developers in Nashville, with the plans, selections and site drawn as one set.
G-590Questions
Questions builders ask about this.
Can I use the template in Excel or Google Sheets?
Yes. It is a CSV file, which opens in Excel, Numbers and Google Sheets. Add your own rooms and rows, then save it as a spreadsheet to keep column widths and formatting.
Is a finish schedule the same as a selections sheet?
They overlap. A selections sheet is usually what an owner or buyer signs off on, with images and options. A finish schedule is the version the field and purchasing use, with exact product names, quantities and dates. Some teams treat the selections sheet as the source and the finish schedule as the output.
Do interior designers do construction?
No. An interior designer specifies finishes and fixtures and coordinates them with the builder. The builder and the trades install them. How much coordination a designer provides is set in each agreement.
Why does the template leave lead times blank?
Lead times depend on the supplier and the product, and they change. We would rather you record a number you confirmed than one we guessed. Ask the supplier, write down the date they told you, and work out the order-by date from it.
How often should a finish schedule be updated?
Whenever a selection changes, and as a dated version every time it goes to the field or to purchasing. If a change affects price or schedule, handle it as a change request under your contract.